SILCHAR– The Union Cabinet has approved a ₹2,014-crore greenfield airport in Doloo, Assam, alongside a ₹4,288.26-crore expansion project at Kamarajar Port in Tamil Nadu. The decisions, cleared by the Cabinet Committee on Economic Affairs on November 25, 2026, represent a major infrastructure push aimed at improving regional connectivity and strengthening India’s transport network.
The proposed airport near Silchar (IXS) will be developed by the Airports Authority of India (AAI) to address limitations at the existing airport and accommodate increasing passenger demand in southern Assam. Meanwhile, the second container terminal at Kamarajar Port will add significant cargo-handling capacity and improve maritime connections with international trade routes.

Doloo Airport Development Plans Gain Momentum
The new greenfield airport will be constructed at Doloo in Assam’s Cachar district, serving the strategically important Barak Valley.
The existing Silchar Airport operates as a civil enclave on defence-controlled land, limiting opportunities for infrastructure expansion and creating operational constraints.
The proposed terminal building will cover 12,351 square metres and accommodate up to 800 passengers during peak hours. It will incorporate modern passenger facilities, sustainable building principles and provisions for future expansion.
A major component of the development is a 2,705-metre-long and 45-metre-wide Code 4C runway designed to support Airbus A320 operations. The airport will also feature an apron with parking capacity for six A320 aircraft and a dedicated isolation bay.
The project is expected to improve air connectivity across South Assam and neighbouring regions. It could also support tourism, trade and local industries by providing better access to the Barak Valley, which has significant tea production and agro-based economic activity.

Kamarajar Port Expansion Boosts Trade And Connectivity
Alongside the aviation project, the Cabinet approved ₹4,288.26 crore for developing a second container terminal at Kamarajar Port Limited in Tamil Nadu. The project will follow a Public-Private Partnership (PPP) model under a Design, Build, Finance, Operate and Transfer (DBFOT) arrangement.
The planned terminal will extend 900 metres and feature a design draft of 18 metres, allowing it to accommodate large container vessels. Once completed, it will provide an additional annual handling capacity of 2 million Twenty-foot Equivalent Units (TEUs).
The project will proceed in two phases. Phase I will receive an investment of ₹2,429.32 crore, while Phase II will account for ₹1,858.94 crore. Kamarajar Port will separately bear an estimated ₹450 crore dredging cost.

Project Timeline And Economic Impact
The port terminal will operate under a 40-year concession agreement, including a 48-month construction period. Phase I is scheduled to finish within 24 months of the concession award, with commercial operations expected to begin in the 25th month.
Construction of Phase II will take place between the 25th and 48th months, allowing full commercial operations to begin in the 49th month.
The expansion is expected to strengthen India’s East Coast maritime infrastructure and reduce reliance on overseas deep-water transshipment hubs. It will also support export-import cargo movements from industrial centres across Tamil Nadu, Karnataka, Andhra Pradesh and Telangana.
The government estimates that the port project could generate around 750 direct and indirect jobs during construction and approximately 800 jobs during its operational phase, MINT Live reported .
Together, the two projects represent an investment of more than ₹6,302 crore. While the Doloo airport will address regional aviation infrastructure requirements, the Kamarajar Port expansion is expected to improve cargo movement and international trade capacity.