State-run plane maker Hindustan Aeronautics Limited (HAL) has set a March 2022 deadline to carry out the first flight of the LCA (light combat aircraft) Mk-1A jet after wrapping up the necessary design activities, HAL chairman R Madhavan said on Thursday.

HAL F404 Engines
HAL will also next week announce a multimillion-dollar engine deal with US firm GE Aviation for 99 F404 engines to power India’s latest indigenous fighter, he said.
The developments come six months after the defence ministry awarded a ₹48,000-crore contract to HAL also for. 83 LCA Mk-1A jets for the Indian Air Force (IAF). The first Mk-1A aircraft will be delivered to the air force by March. 2024, with the rest slated to join its combat fleet by 2029.

“The preliminary design review is over and so is the critical design review for several systems, including mission computer, digital map generator and digital flight control systems.
We are integrating the active electronically scanned array (AESA) radar and also the electronic warfare suite on the final operational clearance (FOC) version of the LCA. After it is proven there, we will integrate it on the final Mk-1A version,” the HAL chairman said.
AESA radar provides superior detection, tracking and targeting capabilities.
Moreover a regulatory body under the Defence Research and Development Organisation (DRDO), CEMILAC is responsible for the airworthiness certification of military aircraft, helicopters, aero-engines and air-launched weapons.
The Aircraft’s Delivery
The delivery schedule requires HAL to provide the IAF with the first two aircraft in 2024, eight in 2025 and the remaining in batches by 2029 at the rate of 14 to 16 fighters every year.

“We are working on a tight schedule, but HAL may deliver all the aircraft ahead of time. We will deliver a new aircraft with significant changes three years after the signing of contract. Even foreign original equipment manufacturers (OEM) take about five to six years to do something like that,” the HAL chairman said.
He also said the deal for the F404 engines for the Mk-1A aircraft had been finalised, with. HAL striking a good bargain with GE Aviation after several rounds of negotiations. Expected to be worth around $700 million. Moreover the engine deal is the biggest contract being awarded by HAL for the project.
LCA MK 1A
The existing LCA variants use the same engine.

“We have got a good price from GE Aviation after 17 to 18 rounds of negotiations. HAL is also holding discussions with its entire vendor base for reducing cost as the volumes are higher. The target is a price reduction of 15% to 20%,” Madhavan said.
MK 1A Features
- HAL has set a deadline of November 2021 to place purchase orders for raw materials. So that machining activities can begin next year onwards, he said.
- The Mk-1A variant will come with:
- digital radar warning receivers
- external self-protection jammer pods
- AESA radar
- advanced beyond-visual-range (BVR) missiles
- and significantly improved maintainability.
- The fighter’s indigenous content is expected to be around 60%, compared to 50% in the existing variants.
- “HAL now has to perform since the stakes involved are very high — IAF’s potency is dependent on it.
- HAL’s work culture and ethos have to turn a new leaf to ensure that aircraft production timelines are met.
- Rigid adherence to quality in production and also timely provisioning of spares would define successful contract implementation. Air Vice Marshal Manmohan Bahadur (retd), former additional director general, Centre for Air Power Studies, previously told HT.

Information Source: Hindustan Times and NDTV
Also read: GO FIRST announces SPECIAL OFFERS for Independence Day and Raksha Bandhan.
Read also: How the upgraded SHIRDI AIRPORT will boost travel.
Stay Tuned and Stay Informed with us. Subscribe for more and also have a CHEERFUL day ahead!